Case
Studies

Temperature Controlled Warehouse Partitioning For Banana Storage

case-study-icon-1

Client

A major food logistics distributor

case-study-icon-2

Industry

Food storage and distribution

case-study-icon-3

Solutions

Temperature control HVAC system

case-study-icon-4

Total KW

900kw cooling 220kw heating

Temperature Controlled Warehouse Partitioning For Banana Storage- Project Overview

This temperature controlled warehouse partitioning project was certainly one of the largest and most challenging we have ever carried out. Measuring at 288,000 sq/mt and at a height of 20 metres, this area was partitioned from the main deep chill warehouse for a banana storage chamber.

6 Key Features For Successful Warehouse Temperature Controlled Partitioning;

  1. Air flow, air-flow, air-flow! You will need high volume fans to reach all areas for temperature controlled warehouse partitioning.
  2. AHU positioning, safely get the units to where they are needed.
  3. Good control strategy for heating and cooling- stay close to set-point
  4. Reliability, no single points of failure- use multiple independent systems
  5. Check power supplies and that local distribution boards have capacity
  6. Fit the equipment carefully, fully commission and test
Temperature Controlled Warehouse Partitioning for Banana Storage
I high level shot of part of the warehouse. The temporary air handling units where mounted on scaffolding platform to raise them above the product for better air projection over the boxed bananas.

This photo shows all the components parts that generally make up a temporary chilled storage cooling system. Including, 2x 25kw low temperature AHU’s with defrost controller, chilled water hosing and a power distribution box and cabling

How Did It All Go?

If we were being honest, we far exceeded our expectations. Temperature control was excellent, within 0.5 of a degree around set-point.

However; air-flow, remember that? and lack off, caused some problems around the tightly packed pallets. We overcame this issue by increasing space between the rows, increasing air penetration.

All in all, a challenging, but very satisfying project to be involved with.

Temperature Controlled Warehouse Partitioning for Banana Storage
The high level units were lifted to the gantry using a telehandler. This operation was safely carried out due to the units sturdy lifting frames

How We Did It

One of the most important elements of this project would achieving good airflow around the area.

Because of this, and after a lot of head scratching, it was decided to take the difficult option and mount six units on the high level gantry. Another 12 were mounted on scaffold platforms on the rear wall of the warehouse.

The intention being to circulate the air effectively around the warehouse. Once this decision was made, careful attention was paid to the planning of this operation. Of paramount concern, was safety- when your lifting 700kg of air handling unit 17mt in the air, it needs to be safe. That’s why we enlisted the help of a professional lifting company with a telehandler.

It was tricky, but in the end all six AHU’s made it safely onto the gantry. The remaining 12 AHU’s were fitted in pairs onto scaffolding platforms at the rear of the warehouse.

Two chilled water cooling systems were used with a total capacity of 950kw. The chillers were located externally and piped with 10 bar rubber suction hosing. For quick installation, our pipe-work systems use Camloc hose connections and branch fittings. Its a great system, and very reliable.

Heating of the air was by electric heater banks fitted to the AHU’s- 18kw’s total each.

What about control? We set-up two control zones, one for the the low level AHU’s and the other for the high level. One AHU on each zone was set-up as a master, controlling all slave unit’s heating and cooling functions.

All in All, quite a challenge to design plan and install this temperature controlled warehouse partitioning project. But thats why we do this, right?

A High Level Walk-Around of this Temperature Controlled Warehouse Partitioning Project

How We've Helped Others In Your Sector

Products Used In This Case Study

50kw Low Temperature AHU Hire

Product

50kw Low Temperature AHU Hire

Our 50 KW Air Handling Units (AHUs) are the ideal solution for any commercial or industrial cooling applications. They can be hired, installed and working onsite with as little as 24 hours’ notice.

'.$post->post_title.'
600kw Chiller Hire

Product

600kw Chiller Hire

600kw chiller hire made easy…..

'.$post->post_title.'
350kw Chiller Hire

Product

350kw Chiller Hire

350kw chiller hire made easy…..

'.$post->post_title.'
Trane Chiller hire

Product

Trane Chiller hire

Very reliable self contained Trane chiller hire from ACR. The ECGAN range are compact powerful machines with excellent controls from one of the leading manufacturers.

'.$post->post_title.'
Chilled Water Hose Hire

Product

Chilled Water Hose Hire

Temporary chilled water hose and ancillaries rental from Advanced Climate Rentals.

'.$post->post_title.'
Left Menu Icon